5" Slabs, Not 4"4.8★ · 310+ reviewsWe Won't Pour Cold Without Blankets3-Year Workmanship Warranty
Flatwork & Foundations · Kansas City, MO

Kansas City Concrete Contractor

Driveways, garage slabs, patios and footings across the metro. Five-inch slabs as standard, rebar rather than mesh, and our own crew on every pour — we have never subbed a job out.

22Years in the Metro
5"Standard Slab Thickness
3yrWorkmanship Warranty
0Jobs Subbed Out
a concrete slab surface with clean sawn control joints running across it
The Thing Nobody Tells You

Every Slab Cracks. The Job Is Choosing Where.

Concrete shrinks as it cures, and shrinking concrete cracks. That is not a defect and no contractor alive can pour a slab that never cracks. Anyone who promises you one is either lying or has not poured much.

What a good contractor actually controls is where it cracks. Control joints, cut at the right depth and the right spacing, give the slab a weak line to fail along — so it opens there, straight and hidden, rather than wandering across the middle of your driveway.

  • Joints cut within 12 hours, at a quarter of the slab depth
  • Spacing at roughly 2.5× the thickness in feet — 5" slab, ~12ft grid
  • We show you the joint layout before the truck arrives
  • Random cracking inside 3 years is on us, in writing
Where the Price Difference Lives

What You're Actually Comparing Between Two Quotes

Two concrete quotes for the same driveway can differ by 40%. It is almost never the labour. It's these five lines, and most quotes don't spell any of them out.

Thickness — 4" or 5"

Four inches is code-minimum for a residential driveway. Five is 25% more concrete and roughly double the load capacity. We pour five as standard. If a quote doesn't say, assume four.

Rebar or wire mesh

Mesh is cheaper and, laid on the ground before the pour, does very little — it needs to sit mid-slab. We run #4 rebar on chairs at 18" centres. Ask any bidder what holds theirs up.

The base under it

Four to six inches of compacted gravel, plate-compacted in lifts. Pouring onto native clay is the single most common reason a KC driveway heaves in its third winter.

Curing

Concrete gains strength by staying wet, not by drying. We cure with compound or blankets for seven days. A slab left to dry out in July can lose a third of its final strength.

The weather it went down in

Below 40°F concrete barely gains strength; above 90°F it flashes off. Both are recoverable with blankets, ice or an early start — all of which cost money, which is why some crews skip them.

Before You Fall For It

Stamped Concrete Has an Ongoing Bill

We install a lot of it and it looks superb. It is also the one product we sell that we make a point of talking people out of when the maintenance doesn't suit them.

It needs resealing every 2-3 years

Roughly $0.50-$0.90 a square foot each time in this market. On a 600 sq ft patio that's $300-$550 every couple of years, forever. Skip it and the colour goes chalky and flat.

Sealer is slick when wet

A sealed stamped surface around a pool or on a slope needs grit additive in the sealer. We add it as standard; plenty don't, and you find out the first wet morning.

Repairs never match

If a section has to come out, the new colour will not match the weathered old one. Plain broom-finish concrete is far more forgiving to patch.

When we'd still say do it

A patio you'll look at every day, a pool surround, an entry — somewhere the appearance earns the upkeep. For a driveway that carries a truck and gets salted, we'd talk you out of it.

wet concrete running down a mixer truck chute on a job site
Why We Sometimes Say No

We Won't Pour Cold Without Blankets

Below about 40°F, cement hydration slows to a crawl and effectively stops near freezing. A slab poured into a cold snap without protection can end up at a fraction of its design strength — and it will look completely fine on the day.

So from November to March we either protect the pour with insulated blankets and a hot-water mix, or we tell you to wait. It costs us jobs every winter to the outfit that just pours it.

  • Blankets and hot water in the mix from November through March
  • We'll postpone rather than pour into a hard freeze
  • Summer pours start at 6:30am to stay ahead of the heat

How a Pour Runs

Most residential jobs are three days on site, spread over a week.

1

On-site estimate

We measure, dig a test hole to see what's under it, and check drainage. Written price in two days with the thickness, the steel and the base spelled out as separate lines.

2

Tear-out & base

Day one. Old concrete out and hauled, grade cut, four to six inches of gravel in and plate-compacted in lifts.

3

Forms & steel

Day two. Forms set to the fall we agreed so water runs away from the house, rebar tied on chairs. You'll see the joint layout marked before anything is poured.

4

Pour & finish

Day three, early. Placed, screeded, floated, broom or stamp finish, joints cut the same day, then cured under compound or blankets.

5

Back on it

Foot traffic at 24 hours, cars at seven days, heavy vehicles at 28. We come back at the end of week one to check the joints have opened where they should.

Metro Customers

What People Say Three Winters Later

They turned up in March, looked at the forecast and told me they weren't pouring that week. Another outfit would have taken my deposit and poured it. Two weeks later it went down in the right weather and it's perfect.
Duane K.Driveway Replacement · Waldo
Asked why theirs was more than the other quote. Answer was five inches instead of four, rebar instead of mesh, and a real base. He drew it on the back of the estimate. Nobody else even mentioned it.
Priya N.Garage Slab · Overland Park
There are two control joints across my patio and I know exactly why they're where they are, because he explained it before they poured. Three winters later the only cracks are in those joints. That is apparently the point.
Marcus B.Stamped Patio · Brookside
Cleanest job site I've had. They washed the chute out into a tub they brought and hauled it off. My neighbour's contractor rinsed his straight into the storm drain last summer.
Eleanor T.Walkway & Steps · Northland

Straight Answers

How long before I can park on it?

Walk on it after 24 hours, park a car at seven days, put anything heavy on it at 28. Concrete keeps gaining strength for years, but 28 days is where it hits its design number.

Will it crack?

Yes — every slab does. The joints are there so it cracks along them instead of across the middle. Random cracking within three years is covered by our workmanship warranty; joint cracking is the system working.

Why is your quote higher?

Usually five inches instead of four, rebar instead of mesh, and a compacted gravel base. Ask the cheaper bidder to write those three lines on their quote — that's normally the whole gap.

Can you match my existing concrete?

Not exactly. New concrete cures lighter and takes a year or two to weather in. If matching matters, replacing the whole area beats patching a section.

Do you do repairs, or only replacement?

Both, but we'll tell you honestly which one your slab wants. Resurfacing a driveway with a failing base is money spent twice.

What happens to the washout?

It goes into a tub we bring and leaves on our truck. Rinsing a chute into a storm drain is illegal in Kansas City and it is also just a poor way to treat somebody's street.

a concrete finisher power-trowelling the surface of a freshly poured slab
Free On-Site Estimate

Come and Stand on It With Us

We price flatwork off the square footage and what's underneath, so we need to see it. Fifteen minutes on site, written price in two days.

Get an Estimate

Tell us what you're thinking about and we'll come and measure. No charge, and no deposit until the forms are ready to set.

Get an Estimate